| Step 4: Pour Footings August 25 - 8:00 a.m. The footings crew comes --and they leave. The excavation was not quite right in the northeast corner. We got all excited for nothing - this might be our theme song... August 25 - 4:00 p.m. The penitent excavator returns (not an easy thing to do) getting his equipment up our road is a real operation! And in an hour fixes the problem. Now we can't get the footings guy back! He has jobs lined up as far as you can see. September 5 At last, they return and put up the forms. But nobody delivered the rebar! September 6 Rebar delivered, but no crew! September 11 FINALLY! The footings crew returns and pours the footings. Real proof we are building a house! |
|